The final welfare installation is now complete, alongside the successful erection of tower cranes 1 and 2. Piling at lower level has also been completed, while slab pouring for the first floor of Block D and bulk excavation are progressing well as construction continues to move forward on site.

Our timelapse cameras continue to capture the latest progress at 100 Chalk Farm Road, documenting key stages throughout the development lifecycle.

We are planning to hold our next community meeting in April 2026 and look forward to sharing further updates with local residents.